Roofs replaced over buildings that never closed

Square footage, schedules and downtime for every project. Client names are withheld at their request.

Aerial view of a long distribution warehouse roof beside a truck lot

Featured / Distribution

284,000 sq ft over a 24/7 pick floor

A 1998 roof with 31 open leak tickets in one winter. The operator could not stop picking for a single shift.

  1. Week 0

    Infrared scan and 14 core cuts. 18 percent of the insulation was wet, concentrated near three drains.

  2. Weeks 1 to 2

    Wet sections removed and re-insulated at night, each zone dried in before 6 AM.

  3. Weeks 3 to 9

    60 mil TPO recover in 20 zones, sequenced with the operations team so no aisle lost power or light.

  4. Closeout

    Seam probe logs, drone survey and a 20-year manufacturer warranty.

0 hoursof operating downtime
31 to 0leak tickets, winter over winter

More projects

Filter by sector

Every case lists the area, the system and what it cost the client in downtime.

Large modern gray warehouse with tall closed doorsCold storage

Joliet cold storage

Infrared scan found 9 percent wet insulation. We replaced only those sections and coated the rest.

Area
118k sq ft
Saved
$412k
Downtime
0 hours
Red brick factory building with large ducts and dust collectors on the roofManufacturing

Cicero metal plant

Two-ply modified bitumen around 46 curbs and a dust collector platform, with walkway pads to every unit.

Area
190k sq ft
Curbs
46
Downtime
0 hours
Three-story brick school with exterior pipes along the wallK-12

Northwest side school

EPDM replacement between the last day of school and teacher institute day, with daily dry-in.

Area
61k sq ft
Schedule
7 weeks
Leaks since
0
Aerial view of several large flat-roofed industrial buildings with white roofsMedia campus

Production studio campus

Restoration coating on six sound stages, scheduled around shoot days with a quiet-work plan.

Area
226k sq ft
Buildings
6
Shoots lost
0
Aerial view of downtown Chicago towers and low-rise rooftopsMultifamily

South Loop high-rise

PVC roof and amenity deck waterproofing, with every material lifted by crane on two Sunday mornings.

Area
38k sq ft
Crane days
2
Units affected
0
Gray building wall with three rooftop exhaust vents against a blue skyHigher ed

Community college lab wing

PVC over fume hood exhaust, with chemical-resistant flashing and a quarterly inspection schedule.

Area
42k sq ft
Exhausts
28
Downtime
0 hours
"They sequenced 20 roof zones around our pick schedule and never once asked us to move a rack. The leak tickets went from 31 to zero."
Operations Manager / distribution center, Elk Grove Village

Your building next

Plan the work around your operation

Tell us how the building runs. We build the schedule around it before we price the roof.

Leak line Request assessment